|
The aim of this dissertation is to consider how the introduction of the Civil Procedure Rules (“CPR”) has affected dilapidation claims with particular emphasis on the role played by the expert witnesses. In considering this question it is also important to look at the broader picture and consider the general changes brought about by the CPR to English litigation, as well as the reasons behind the need for such changes.
Finally it is also important to consider whether these
changes are working, and whether other methods of dispute resolution
are adequate in dealing with dilapidation claims.
This dissertation has accordingly been divided into four chapters.
Chapter one provides a background to the reforms brought about by Lord
Woolf, chapter two considers how the CPR generally affects dilapidation
claims, chapter three considers the role of the expert witness and
chapter four considers other methods of dispute resolution that may be
suitable in dilapidation claims. This is followed by a conclusion
considering how and whether the CPR has been successful in changing the
litigation process as so desired by Lord Woolf.
Chapter One
Background to the introduction of the CPR
When enacted, the CPR was proclaimed to be a new procedural code. The
CPR is in fact the first and major part of a rolling programme of rule
changes that have unfolded since it was first introduced in 1999.
Notably since 1851, there have been over 60 reports dealing with small
or large aspects of reform in the fields of English procedure, both
civil and criminal.
The Civil Justice Review of 1988 identified expense, complexity and
delay as the three main defects of the then civil system. The
Heilbron/Hodge report 1993 aimed further blows at the system and it was
perhaps as a result of this report that Lord Woolf was appointed in
1994 by the then Lord Chancellor (Lord Mackay) to review the system of
civil procedure with a view to reform.
Lord Woolf’s two reports, interim and final, provide the blue-print
for profound changes introduced in April 1999. One commentator said
that the Woolf enterprise of radical reform is “a noble enterprise
which ought to be applauded and supported.” It is true to say that the
CPR represents the greatest shake-up in civil procedure since the
1870s, when the common law and equity jurisdictions were fused in a
combined High Court, or since the withering of civil juries during the
last 100 or so years.
The three major problems of the old system of civil procedure
identified by Lord Woolf, correspond with those already described in
the Civil Justice Review in 1988 already referred to above, namely the
high cost of litigation, delay and complexity. It was also seen as
unequal and unjust,
“the defects I identified in our present system were that it is too
expensive in that the costs often exceed the value of the claim; too
slow in bringing cases to a conclusion and too unequal: there is a lack
of equality between the powerful, wealthy litigant and the under
resourced litigant. It is too uncertain: the difficulty of forecasting
what litigation will cost and how long it will last induces the fear of
the unknown; and it is incomprehensible to many litigants. Above all it
is too fragmented in the way it is organised since there is no one with
clear overall responsibility for the administration of civil justice;
and too adversarial as cases are run by the parties, not by the courts
and the rules of court, all too often, are ignored by the parties and
not enforced by the court.”
Lord Woolf was particularly concerned with the problematical
adversarial “culture” found within English litigation, “the adversarial
process [namely the absence of judicial control] is likely
to…degenerate into an environment in which the litigation process is
too often seen as a battle field where no rules apply.” As reported
by the Chancery Judge Mr Justice Lightman, “in cases before me I have
had “blue chip” firms carrying on at their clients’ expense feuds with
each other in the form of vitriolic correspondence and total
non-co-operation during the trial, where I have had to act as a
mediator between them. If the price of impressing clients is indulging
in these tactics, it is a price which no [practitioner] can afford to
pay consistently with his duty to the Court, and the sanctions for
breach of this duty must be real enough to deter recurrence.”
Lord Woolf also referred to a wasteful system which leads to “every
aspect of the case [being] fully investigated [by the parties]. This
encourages excessive work and cost on issues which are often recognised
from an early stage to be peripheral.” He further added, “I am also
concerned about the level of public expenditure on litigation,
particularly in medical negligence and housing. In both of these areas
substantial amounts of public money are absorbed in legal costs which
could be better spent, in the one case on improving medical care and in
the other on improving standards of social housing. An efficient and
cost effective justice system is also of vital importance to the
commercial, financial and industrial life of this country and I was
anxious to improve this, especially because of the evidence I received
that there was a substantial risk of the existing system changing our
competitive position in relation to other jurisdictions. Finally I was
anxious to ensure that the judiciary and the resources of the Court
Service were deployed to the best effect.”
In order to carry out this task, Lord Woolf set out his proposals to
“change the landscape” of litigation in paragraph 9 of his final report
on Access to Justice.
His proposed changes included the fact he wanted litigation to be
avoided whenever possible. He wanted potential litigants to be
encouraged to start court proceedings to resolve disputes only as a
last resort, and only after using other more appropriate means of
resolving their dispute when these are available. He accordingly
suggested that information on sources of alternative dispute resolution
(ADR) be provided in all civil courts. Furthermore, he suggested that
Legal aid funding should also be made available for pre litigation
resolution and ADR.
Protocols in relation to medical negligence, housing and personal
injury, and additional powers for the court in relation to pre
litigation disclosure, were also an important addition, as these would
enable parties to obtain information earlier and promote the settlement
of cases.
Another important feature of the new regime, would be the provision
that in commencing litigation both parties would be able to make offers
to settle the whole or part of a dispute. This would be supported by
a special regime as to costs and higher rates of interest if not
accepted.
In seeking to make litigation less adversarial and more co operative,
Lord Woolf proposed that there should be an expectation of openness and
co operation between parties from the outset, supported by pre
litigation protocols on disclosure and experts. The courts would
further be able to give effect to their disapproval of a lack of co
operation prior to litigation. Furthermore, the court would play a
greater role in encouraging the use of ADR at case management
conferences and pre trial reviews, and would take into account whether
the parties have unreasonably refused to try ADR or behaved
unreasonably in the course of ADR.
The duty of experts to the court would be emphasised. Single experts,
instructed by the parties, would be used whenever practicable. Opposing
experts would be encouraged to meet or communicate as early as possible
to narrow the issues between them. The court would also have a power to
appoint an expert when required.
In seeking to make litigation less complex, Lord Woolf proposed there
should be a single set of rules applying to the High Court and the
county courts. The rules would be simpler than the old system, and
special rules for specific types of litigation would be reduced to a
minimum. All proceedings would also be commenced in the same way, by
way of a claim.
Importantly, the claim and defence would not be technical documents.
The claim will work to set out the facts alleged by the claimant, the
remedy sought by the claimant, the grounds on which the remedy is
sought and any relevant points of law. The defence will set out the
defendant's detailed response to the claim and make clear the real
issues between the parties. Both 'statements of case' are to include
certificates by the parties verifying their contents so tactical
allegations would no longer be possible.
During proceedings the court on its own initiative, or on the
application of either party, would be able to dispose of individual
issues or of the litigation as a whole where there is no real prospect
of success, whilst claimants would be able to start proceedings in any
court. The court would be responsible for directing the parties or for
transfering the case (if this is deemed necessary), to a more
appropriate part of the system.
Discovery would also be controlled. Is some cases, when deemed
necessary, the old pre CPR scale of discovery would be possible but in
the majority of cases there would be a new standard test for more
restricted disclosure.
Special procedures, involving active judicial case management, to deal
with multi party actions expeditiously and fairly would also be set up.
Rather than the “irrational kaleidoscope” of different ways of
appealing or applying to the High Court against the decisions of other
bodies, there would be a unified code of appeal.
The timescale of litigation would be shorter and more certain. All
cases would progress to trial in accordance with a timetable set and
monitored by the court (rather than be controlled in the best part by
litigants themselves). For fast track cases there would be fixed
timetables of no more than 30 weeks whilst the court would apply strict
sanctions to parties who do not comply with the procedures or
timetables.
Appeals from case management decisions would be kept to the minimum,
and be dealt with expeditiously. Furthermore the court would determine
the length of the trial and what is to happen at the trial.
Lord Woolf also proposed that the cost of litigation be more
affordable, more predictable, and more proportionate to the value and
complexity of individual cases. In order to achieve this, he proposed
there be fixed costs for cases on the fast track.
Estimates of costs for multi track cases would also be published by the
court or agreed by the parties and approved by the court. There would
be a special 'streamlined' track for lower value or less complex multi
track cases, where the procedure can be made much simpler with
appropriate budgets for costs. In cases where the procedure is
uncomplicated and predictable the court would issue guideline costs
with the assistance of users.
There would also be a new test for the taxation of costs to further the
overriding objective. It would be that there should be allowed "such
sum as is reasonable taking account of the interests of both parties to
the taxation."
Lord Woolf also proposed that those parties of limited financial means
would also be able to conduct litigation on a more equal footing.
Litigants who are not legally represented would be able to get more
help from advice services and from the courts whilst procedural judges
would take account of the parties' financial circumstances in
allocating cases to the fast track or to the small claims jurisdiction.
Limited procedures and tight timetables on the fast track, and
judicial case management on the multi track, would make it more
difficult for wealthier parties to gain a tactical advantage over their
opponents by additional expenditure. Furthermore, when deciding upon
the procedure which is to be adopted the court would, if the parties'
means are unequal, be entitled to make an order for a more elaborate
procedure, conditional upon the other side agreeing to meet, in any
event, the difference in the cost of the two possible procedures. This
new approach would be supported by more effective sanctions, including
orders for costs in a fixed sum which would be paid promptly.
Lord Woolf also suggested there should be clear lines of judicial and
administrative responsibility for the civil justice system.
Accordingly, the Head of Civil Justice would have overall
responsibility for the civil justice system in England and Wales.
The Presiding Judges on each Circuit would exercise their
responsibility for civil work in conjunction with the two Chancery
judges who would also oversee the business and mercantile lists. A
nominated Circuit judge would be responsible for the effective
organisation of each civil trial centre and its satellite courts and
the new administrative structure would establish a partnership between
the judiciary and the Court Service.
Lord Woolf felt strongly that the structure of the courts and the
deployment of judges should be designed to meet the needs of litigants.
In doing so, he proposed heavier and more complex civil cases would be
concentrated at trial centres which have the resources needed,
including specialist judges, to ensure that the work is dealt with
effectively.
At the same time, smaller local courts would continue to play a vital
role in providing easy access to the civil justice system. Housing
claims, small claims, debt cases and cases allocated to the fast track
would be dealt with there, as well as case management of the less
complex multi track cases. Lord Woolf also proposed that better ways
of providing access to justice in rural areas would be maintained and
developed.
Furthermore, the courts should have access to the technology needed to
monitor the progress of litigation and litigants should be able to
communicate with the courts electronically and through video and
telephone conferencing facilities.
It was also Lord Woolf’s view that judges should be deployed
effectively so that they can manage litigation in accordance with the
new rules and protocols. Judges should accordingly be given the
training they need to manage cases and be encouraged to specialise in
such areas as housing and medical negligence.
Cases should therefore be dealt with by the part of the system which is
most appropriate in each instance. The distinctions between the county
courts and High Court and between the divisions of the High Court
should accordingly be of reduced significance.
In maintaining a civil justice system that is responsive to the needs
of litigants, Lord Woolf proposed the courts provide advice and
assistance to litigants through court based or duty advice and
assistance schemes, especially in courts with substantial levels of
debt and housing work. Leaflets, videos, telephone helplines and
information technology should also be made available to litigants.
Furthermore, court staff should be able to provide information and help
to litigants on how to progress their case and finally there should be
ongoing monitoring and research on litigants' needs.
It is these reforms as proposed by Lord Woolf that have so radically
changed the face of English litigation, including to some extent
dilapidation claims as considered in detail in the next chapter.
Chapter 2 - The influence of the Civil Procedure Rules on Dilapidation Claims
Dilapidation cases which do in fact get to court every year are few and
far between, with even fewer still being reported. This is so, despite
the fact that the number of potential claims must annually be tens of
thousands, due to the fact almost every lease or tenancy of any
description of property is likely to impose an obligation to repair
upon the tenant or the landlord or both. Furthermore, in many cases,
it is likely that those obligations would not have been fully complied
with.
This is because, despite the fact landlords and tenants are normally
aware of the potential for such claims, both generally recognise that
the problems are essentially practical ones that ought if possible, to
be settled by negotiation rather than by litigation. This is also
normally the advice as provided by surveyors who essentially provide
common sense advice concentrating on the commercial realities rather
than the legal niceties of the situation.
The Woolf reforms, the approval of the pre-action protocol for Housing
Disrepair cases, the increasing use of the Property Litigation
Associate’s (as yet unadopted) Pre-Action Protocol for Terminal
Dilapidations particularly emphasise settling cases out of court
whenever possible and are likely to continue reducing the number of
dilapidations claims even further.
When considering whether to make a claim for dilapidations against his
tenant, a landlord will be influenced by the nature of the event
prompting him to do so. This includes instances where disrepair
becomes apparent on inspection (obvious examples include disrepairs to
the roof of a building which, if not repaired soon, could lead to an
outbreak of dry rot or to serious damage to the fabric). Further
examples also include instances of assignment of reversion. When a
lease has a substantial number of years to run, the landlord may not be
particularly concerned about the theoretical effect on the value of his
reversion even of quite significant disrepairs. This is because the
theoretical diminution in the value of his reversion is only a loss on
paper. On the other hand, should the landlord wish to sell his
reversion or raise substantial finance on it, the paper loss could
become a reality, in which case he may wish to take effective action to
force the tenant to comply with his covenants. Other instances where
landlords consider whether or not to seek compliance with the repairing
obligations of the lease include instances where a tenant proposes an
assignment of a term, in cases of emergencies (where there is an
unforeseen failure of the part of the structure of the building which
the landlord, either of his own volition or under compulsion from a
statutory authority, wishes to have remedied as a matter of urgency),
in instances where there have been complaints, at the time of rent
review or most commonly at the expiry of the term.
Whether or not a landlord decides to take action, will depend on
three things, namely the event prompting his consideration of the
claim, the nature of the remedies available and the overall assessment
of the benefits of making a claim weighed against the costs and risks
of doing so.
Pre Action Protocols
The CPR reflects the policy that litigation is to be seen as a means of
last resort, to be invoked only when all other attempts at a compromise
have failed. The Pre-Action Protocol for Housing Disrepair Cases
requires extensive steps to be taken with a view to formulating,
clarifying and settling residential disrepair claims in order to avoid
resorting to court procedures. The Protocol is framed in terms
reflecting the practical reality that such claims are almost inevitably
brought by tenants against landlords, rather than vice versa.
Accordingly if a formally adopted pre-action protocol is introduce for
terminal dilapidations claims generally, its procedures will have to be
observed as an essential precursor to the start of proceedings.
Despite the fact that at the time of writing no such protocol has been
formally adopted, the existence of the Property Litigation
Association’s recommended Protocol for Terminal Dilapidations Claims
for Damages will influence practice and is likely to be treated by the
courts as representing best practice (this issue is discussed in more
detail below).
Even prior to the CPR, it was considered courteous and sometimes
essential for an intending claimant to send a “letter before action”
notifying the proposed defendant of the prospective claimant’s
intention to commence proceedings against him. Notably, if the
proposed defendant was willing to satisfy the claim, by either making a
payment or carrying out works in accordance with the letter before
action, court proceedings would not be issued. Letters before action
therefore provide the proposed defendant with a last chance to avoid
litigation, and generally marks the point from which the expenses of
pursuing the claim could be recovered as costs in the proceedings.
In light of the fact one of the aims of the CPR was to reduce the
number of claims that went to court, it places a great emphasis on the
steps which the parties should take so as to settle their differences
prior to the commencement of proceedings. The procedures as introduced
by the CPR, are novel in that they require the proposed defendant (as
well as the claimant) to make a genuine effort in explaining their
position and provide sanctions in cases of default.
The “pre-action protocols” as introduced by the CPR outline the
steps parties should take to seek information from and to provide
information to each other about a prospective legal claim. The
objectives of protocols may be described as being:
(1) to encourage the exchange of early and full information about the prospective legal claim,
(2) to enable parties to avoid litigation by agreeing a settlement of the claim before the commencement of proceedings,
(3) to support the efficient management of proceedings where litigation cannot be avoided.
The Practice Direction refers to CPR, r.3.1 (4) and (5), entitling
the court to take into account compliance or non-compliance with any
relevant protocol when giving directions, and further entitles the
court to order a party who has failed to comply to pay a sum into
court, and to CPR r.44.3 (5) (a), which includes within the conduct
relevant to the exercise of the discretion as to costs “conduct before,
as well as during proceedings and in particular the extent to which the
parties followed any relevant pre-action protocols.”
The Practice Direction further states the consequences which may follow
if, in the court’s opinion, such non-compliance leads to the start of
proceedings that otherwise might not have needed to be commenced, or
has led to costs being incurred in proceedings that might otherwise not
have been incurred (including penalties as to costs and interest). In
such instance, the court will seek to place the “innocent” party in no
worse a position than he would have been in if the relevant protocol
had been complied with. Examples include claimants who may be found to
have failed to comply by not having provided enough information or by
not having followed the procedure as required by the protocol. In the
same way, a defendant may be found not to have complied if for example,
he or she fails to make a preliminary response to the letter of claim
within the time fixed by the relevant protocol, or by not making a full
response within the time fixed or for not disclosing documents that are
required to be disclosed.
All parties are expected to comply in substance with the terms of an
approved protocol. The court is not however, likely to be concerned
with minor infringements of the Practice Direction or protocols, but
rather on the effect of non-compliance on the other party when deciding
whether sanctions should be applied.
At present, and as referred to above, no protocol for general use in
dilapidation cases has been approved by the Lord Chancellor’s
Department for the purposes of the CPR. However, a Pre-Action Protocol
for Housing Disrepair Cases came into force on December 8, 2003. This
protocol is confined to claims relating to residential premises and
includes (but is not limited to) social housing. Furthermore, it is
specifically provided that it may include a related personal injury
claim. Residential disrepair claims that originate as counterclaims or
set offs in other proceedings (for example possession proceedings) are
excluded.
No other approved protocol for use in dilapidations cases exist.
However, after a process of consultation with the judiciary and the
relevant affected professions, the Property Litigation Association has
published a Protocol for Terminal Dilapidations Claims for Damages.
The document was the result of work by the Sub-Committee on Law
Reform and members were invited to consider it, provide feedback on it
and, if appropriate, use it.
On 14 November 2000 a seminar was further held in London, where a
panel of surveyors as well as solicitors and judges were invited to
express their views on the proposed protocol. The Protocol has since
been sent to the Lord Chancellor’s Department for adoption as an
approved Protocol under the CPR although at this stage it has no
official status other than it represents the Property Litigation
Association’s recommended process for conducting terminal dilapidations
claim.
Despite this fact RICS has annexed the Protocol to their updated
Guidance Note on dilapidations claim meaning that it is likely to be
frequently used by surveyors, with the result that even if it is not
approved by the Lord Chancellor’s Department, it is likely to become
industry standard.
Accordingly, for the time being, the present position (except in
residential cases) is governed by paragraph 4 of the Practice Direction
– Protocols which provides that:
“In cases not covered by any approved protocol, the court will
expect the parties, in accordance with the overriding objective and the
matters referred to in CPR 1.1(2)(a) (b) and (c) to act reasonably in
exchanging documents relevant to the claim and in trying to avoid the
necessity for starting proceedings.”
It is however, reasonable to expect that the court will accept the
suggestion made in the introduction to the Protocol for Terminal
Dilapidations Claims for Damages that it should treat the standards set
out in the protocol as the normal reasonable approach to pre-action
conduct when the court considers the issue of costs and other sanctions
under the CPR.
Jurisdiction
The CPR abolished, for the most purposes the distinctions between
claims that were within the jurisdiction of the High Court and the
County Court. This means that questions raised as to which court is
most suitable to hear a particular matter continue to exist, but such
questions will largely be dealt with by the process of transfer from
one court to another and not by formal limits on jurisdiction.
Notably, an exception to this may be claims for leave under the
Leasehold Property (Repairs) Act 1938. Apart from this particular
instance, the case management of dilapidations claims will be treated
in the same way as any other civil proceedings under the CPR. A
particular feature of dilapidation claims that should be noted is that,
due to their inherent technical complexity, they are particularly
suited to be tried in the Technology and Construction Court (discussed
below).
The Technology and Construction Court
“Official Referees” as the judges of the Technology Court were
previously known, specialise in certain types of cases including cases
involving defective buildings or building work. This makes them well
suited to trying many types of dilapidation cases. Even before the CPR
the Technology and Construction Court had already developed special
procedures and directions that were suitable for complex cases. When
the CPR was first introduced, proceedings in the Technology and
Construction Court were considered as “specialist proceedings” under
r.49.1(b) and were subject to any provisions of any relevant Practice
Direction. Since 25 March 2002, the procedure in the Technology and
Construction Court has been governed by Part 60 of the CPR and the
Practice Direction “Technology and Construction Court Claims”
supplementing Part 60.
It is important to note that claims may only normally be brought in the
Technology and Construction Court, if it involves issues or questions
that are technically complex or a trial by a Technology and
Construction Court judge is desirable. Examples provided by the
Practice Direction include claims between landlord and tenant for
breach a repairing covenant.
The Leasehold Property (Repairs) Act 1938
Section 6 of the 1938 Act expressly provides that the appropriate court
for an application for leave to be made is the county court, unless the
proceedings by action for which leave may be given has to be taken in a
Court other than the County Court, in which case the application should
be made to that other court.
In light of the changes made by the CPR (as well as earlier changes
made by the Courts and Legal Services Act 1990 and the High Court and
County Courts Jurisdiction Order 1991), there is now no instance in
which proceedings for either forfeiture or damages or both to have to
be taken in the High Court and such proceedings may now be taken in
either court. I would seem to follow that an application for leave
under the Act, must therefore be brought in the county court, and that
the High Court no longer has jurisdiction to grant leave. This point
is less important than it used to be, since there is no longer any
difference in procedure between the High Court and the County Court,
although if proceedings are commenced in the incorrect court and
subsequently need to be transferred, this may result in delay and
additional cost.
An application for leave will normally be brought by means of
proceedings under CPR Part 8 “Alternative Procedure for Claims.”
However, in cases where there is likely to be a significant dispute as
to fact it would be preferable for the proceedings to be commenced by
issuing a claim form under Part 7, although it is doubtful whether this
is permissible under the CPR. Accordingly, it is advisable to start
such proceedings under Part 8 and to seek appropriate directions under
the case management powers of the court where, because disputed issues
of fact arise or for other reasons, it is unsatisfactory to proceed as
an ordinary Part 8 claim.
Evidence in 1938 Act Applications
Since the decision in the case of Associate British Ports v C.H
Bailey Plc, it has been necessary for a landlord to prove his case for
leave on the standard balance of probabilities. This includes the
service and validity of the s.146 notice, the existence of breaches of
covenant, the existence of grounds under s.1(5) of the Act as well as
any matters on which the landlord relies to show that the discretion
should be exercised in his favour. Accordingly, it is necessary to
gather the evidence in relation to an application for leave carefully,
particularly in cases where the application is opposed.
If proceedings are commenced under Part 8, the landlord as Claimant
must file any written evidence he seeks to rely on, at the same time as
he files his claim form, and must serve it on the defendant when
serving the claim form. The evidence will usually be in the form of
witness statements, although in addition, the claimant can rely upon
any statement in the claim form as evidence, so long as this is
verified by a statement of truth. The normal rules of evidence apply,
meaning any reliance on hearsay evidence will be subject to the
restrictions and safeguards imposed by the Civil Evidence Act 1995 and
expert evidence may only be relied upon if permitted by the court.
The defendant thereafter has to acknowledge service within 14 days
after service of the claim form, and at the same time serve any written
evidence upon which he intends to rely. This may be difficult if
expert evidence is to be relied upon of if there is a dispute about the
detail of the schedule of dilapidations, meaning the defendant is
likely to seek the court’s permission to serve evidence outside the
time limit.
The court may allow or require a party to give oral evidence at the
hearing and may give directions for the attendance for
cross-examination of a witness who has given evidence. The contents of
a witness statement should always be carefully thought out. Under the
procedures prior to the CPR, affidavits were often relied upon which
failed to adequately explain the true nature of the grounds and
supporting facts upon which the application was based. This was
criticised by Megarry V.C in the case of Land Securities Plc v Receiver
for the Metropolitan Police District where the landlord’s evidence was
criticised as follows, “the evidence is not impressive. Expressions of
opinion by a chartered surveyor which do little more than apply to the
building something of the language of paragraphs (a) (b) and (e) [of
section 1 (5) of the 1938 Act] and wind up with a watered down version
of (e), obviously leave a good deal to be desired.”
Accordingly, following the decision in Associated British Ports v B.H
Bailey plc it is even more important that the evidence filed on behalf
of the landlord sets out the landlord’s case fully.
Summary Judgment
Part 24 of the CPR provides the court with powers to give summary
judgment against a claimant or defendant on the whole of a claim or on
a particular issue if it considers that the claimant has no real
prospect of succeeding in the claim or issue or that the defendant has
no real prospect of successfully defending the claim or issue, and that
there is no other reason why the case or issue should be disposed of at
a trial.
Part 24 departs from the former RSC Ord. 14 in the ability with which
it gives to the defendant to apply for summary judgment. However, it
is thought that summary judgment will rarely be given in favour of a
defendant in a dilapidations claim (except in cases where the defendant
relies upon the second limb of s.18(1) of the Landlord and Tenant Act
1927).
An application for summary judgment is made by an application notice
before the master or district judge. Evidence in support can either be
contained in the claim form or in the application supported by the
appropriate statement of truth, or in a witness statement served with
the application. Paragraph 2 of the Practice Direction supplementing
Part 24 requires the application notice or evidence to identify
concisely any point of law or provision in a document on which the
applicant relies and/or state that the application is made because the
applicant believes that on the evidence the respondent has no real
prospect of succeeding on the claim or issue, or of successfully
defending the claim or issue to which the applicant relates and that
the applicant knows of no other reason why the disposal of the claim or
issue should await trial.
It is likely in dilapidation claims that applications for summary
judgment for damages to be determined at a further hearing are likely
to be made where it is obvious that there exist at least some items of
disrepair for which the defendant is liable. If so, the claimant will
seek to argue that even if one breach can be shown to exist, he or she
must be entitled to judgment in his favour.
Two arguments exist against this. Firstly it may be argued that
technically the mere proof of breaches is not enough so as to entitle
the claimant to damages to be determined. Arguably, the claimant will
also have to prove that the existence of the proved breach or breaches
has caused a diminution in the value of his reversion, as otherwise he
or she will not be entitled to any damages, including nominal damages,
by virtue of the provisions of s.18(1) of the Landlord and Tenant Act
1927. Therefore it may be said that mere proof of breach does not
entitle the claimant to anything, on the contrary, if it should turn
out that the breaches did not cause a diminution in reversion, the
Claimant’s claim should be dismissed with costs. This argument may be
successful in cases where only a small number of breaches can
definitely be proved and it is less likely to prevail in cases where it
is obvious that there are a large number of items for which the
defendant is responsible. Accordingly in that instance the court may
conclude that it is sufficiently likely that some diminution has been
caused for judgment for damages to be determined to be appropriate.
Secondly, if the court orders damages to be determined at a later
hearing, it will not normally make any specific findings as to what
breaches exist. Accordingly it follows that whoever subsequently
determines the amount of damages will in effect be trying the question
of breaches for a second time. Even if the court finds that a
particular breach exists at the hearing of the application for summary
judgment, the nature of that breach will have to be gone into again on
the determination of damages, because it will be relevant at that stage
to consider what is the appropriate remedial work. This is illustrated
in instances where the court may find on the application for summary
judgment that for example the roof covering is defective. That fact is
sufficient to establish a breach, but so as to determine damages, it
will be necessary to enquire whether the covenant requires the roof
covering to be replaced in its entirety, or whether localised patch
repairs will do. It is thought that for these two reasons, summary
judgment will normally be an unnecessary extra step that does not
really achieve anything in dilapidation cases, and will tend to delay
the final judgment as well as increase costs.
A further complication arises where the claimant’s claim is not for
damages at the expiry of the term but for forfeiture of the lease and
damages. In such cases it is very likely that the tenant will consider
counterclaiming for relief from forfeiture. Accordingly, provided that
the tenant’s claim is bona fide and has at least some prospect of
success, the court cannot make an order for possession under Part 24
pending the trial of the counterclaim. The court that hears the
application will have to decide what the items of disrepair for which
the defendant is liable actually are, how serious those breaches are,
the circumstances under which the breaches arose and whether the
defendant ought to be granted relief upon terms that he carry out a
specific schedule of works. This type of investigation is of
essentially the same matters that would have to be investigated on the
determination of damages. Accordingly it would be necessary to ensure
that the application for relief and the determination were heard by the
same court as part of the same hearing.
It is accordingly thought that in many instances where the claimant
seeks summary judgment for damages to be determined, the court ought
properly to conclude that there is another reason why the case or issue
should be disposed of at a trial within the meaning of Part 24.2(b).
In such cases it seems that the court should dismiss the application as
the court will no longer follow its former practice of giving leave to
defend.
For the reasons discussed above, in most cases there will be little
to be gained by an application for summary judgment for damages to be
determined, save possibly a dent in the tenant’s morale by having lost
the first round. More importantly, judgment for damages to be
determined carries with it the risk that further items of disrepair,
for which the tenant it liable, may be discovered after judgment. Once
judgment has been given, it will not be able to amend existing
proceedings so as to provide details of new breaches. At the worst
case scenario, new proceedings may be struck out under CPR, r.3.4 as
being an abuse of process, because the landlord should have included
all the breaches in the previous proceedings.
Notably a tenant against whom judgement for damages to be determined
is given, should ensure that the order makes clear that he is, on the
determination, entitled to dispute the individual items in the
schedule. If he or she does not do this, it may be argued on the
determination that the effect of the judgement was that the tenant
cannot dispute anything in the schedule.
Scott Schedules
Dilapidation claims will involve not only the usual pleadings
normally encountered in civil litigation, but also a pleading known as
a “Scott Schedule”. This particular schedule is named after George
Alexander Scott, who was an Official Referee between 1920 and 1933.
The nature of the disputes that were referred to the Official Referees
(now the Technology and Construction Court) involved them in deciding
numerous facts on an item by item basis, and this meant the traditional
forms of pleadings were cumbersome in dealing with such disputes. The
Scott Schedule was a type of pleading that brought both parties ‘ cases
in relation to each of the disputed items together in a tabular format
and more importantly, in a single document. This could be easily
referred to by council, witnesses and the judge during the trial and
facilitated the understanding of evidence. It is now settled practice
for the judge of the Technology and Construction Court, in succeeding
the Official Referees, to order that a Scott Schedule be prepared.
Notably, such a direction may also be made in appropriate cases, by any
court.
The initial burden of preparing the schedule lies with the claimant.
The document must set out under appropriate headings the claimants case
in relation to liability and quantum on an item by item basis. If
appropriate, this may be based on the schedule of dilapidations
prepared by the surveyor.
The purpose of the schedule is to enable both sides to know what the
issues are and it is important that the defendant pleads his case
properly in the Scot Schedule. A bare denial of liability for a
particular item is not helpful in advancing the case. For example,
where the claimant pleads in column (x) that “the roof covering is torn
or holed over approximately 60 per cent of its total area”, the
defendant’s case may the that the roof is not torn or holed at all as
alleged or that the roof is torn or holed, but not to the extent as
alleged by the claimant. Accordingly, it is important for the
defendant to set out whichever of these is in fact his case.
It should be stressed that the Scott Schedule is designed to
encapsulate the parties’ respective cases in relation to the detailed
items of claim, and is taken to be without prejudice to any defence of
a general nature that has been raised in relation to liability or
quantum. In admitting that items of disrepair existed and that
remedial works were necessary to make things right at a certain cost,
the defendant is not admitting that these repairs are in fact his
liabilities under his covenants, or that the cost of remedying the
defects is relevant to the quantification of the claimant’s loss if
any. These general defences should be raised in the defence in the
ordinary way and need to be repeated in the Scott Schedule. This type
of schedule not only works to save time during the proceedings, but
also helps to concentrate the minds of the parties at a relatively
early stage upon the exact nature of their detailed cases, and the
nature and importance of the issues which divide them. Preparing the
schedule at an early stage will give both parties an opportunity to
narrow the differences between them and may help them to reach a
realistic compromise.
Disclosure
Disclosure enables one party to litigation to obtain the right to
inspect and if desired to request copies of documents in the control of
the other party. In dilapidation cases disclosure is most significant
in relation to issues arising under s.18 (1) of the Landlord and Tenant
Act 1927, and in particular whether the landlord intended to redevelop
the premises following the termination of the lease. In such cases
disclosure enables the tenant to see not only those documents that are
available to the public at the relevant time, including planning
applications, but also internal memoranda and other documents
evidencing the landlord’s private thinking on the matter.
CPR Part 31 allows a party to make a reasonable search for documents
that adversely affects their own case or adversely affects or supports
another party’s case and to make and serve on the other parties a list
of those documents. The party must also include in the list any other
documents on which he relies. The disclosing party is then under an
obligation to disclose the documents to the other parties and allow
them to inspect the documents in the list, except where there is a
right to withhold inspection, or where it is considered that it would
be disproportionate to the issues in the case to allow disclosure of
those documents. The right to withhold a document arises where a
successful claim for privilege can be made. Documents that contain
advice from legal advisers on legal matters are absolutely privileged,
but this does not apply to other advice from non-legal advisers.
Accordingly, if a landlord were to take the advice of counsel some
months before the expiry of the lease as to his prospects of obtaining
planning permission for a redevelopment, his instructions to his
solicitor, the solicitor’s instructions to counsel and counsel’s
opinion would all be privileged. However, other advice the same
landlord may have obtained in relation to the proposed development, for
example from a valuation surveyor as to the viability of the scheme,
would not be privileged. Another head of privilege that may be of
relevance in such instances is the head of privilege protecting from
disclosure documents which came into existence with the predominant
purpose of being used in the preparation of actual or contemplated
litigation. The exact boundaries of this privilege are however
ill-defined. It is thought that it would not normally apply to notes
by a building surveyor in the course of his initial inspection of
premises with a view to compiling a schedule of dilapidations, but that
it would cover his notes made on a subsequent visit for the purposes of
pricing a Scott Schedule. It would not cover a valuation of the
demised premises carried out for the purposes of a general valuation of
the landlord’s portfolio, even if the valuer took into account the
state of repair of the demised premises, but it would cover a report
prepared by the same valuer for the purposes of countering the tenant’s
contention that there had been no diminution to the landlord’s
reversion.
Interest
The CPR has not significantly altered the powers or practice of the
courts as to the award of interest. The court has power to award
simple interest at such rate as the court thinks fit or as may be
prescribed on all or ay part of a debt or damages in respect of which
judgment is given, or payment is made before judgment, for all or any
part of the period between the date when the cause of action arose and
the date of payment or judgment, whichever is the earlier. Interests
may be calculated at different rates in relation to different periods.
To award interest is not to punish the defendant but to compensate the
plaintiff for being kept out of his money. Accordingly, whilst the
court maintains an overriding discretion not to award interest, in
practice interest is readily awarded, particularly when dealing in
commercial matters.
In disrepair cases where damages are awarded, interest will normally be
awarded from the date on which the cause of action arose until the date
of judgment. This means that interest on damages for failure to yield
up in repair will run from the term date of the lease until the date of
judgment. Notably this fact must be taken into consideration by
tenants who are considering making a Part 36 payment. The rate of
interest will be within the court’s discretion, but will normally be
the rate payable under the Judgment Act on judgment debts, that is
prescribed from time to time. It is also important to note that the
court cannot award interest on arrears of contractual interest.
In the case of Johnsey Estates (1990) Limited v Secretary of State for
the Environment, Transport and the Regions the diminution in the value
of the reversion was held to be £200,000. Interest was awarded on that
sum from the term date of the lease. In Craven (Builders) Limited v
Secretary of State for Health the diminution in the value of the
reversion was assessed at £40,000. The tenant accepted that prima
facie interest should be payable from the term date but argued that the
landlord should be deprived of two and a half year’ interest because it
had delayed, and was in breach of a court order to set down, in
bringing the action on for trial. In this instance, Neuberger J.
rejected that contention on the principal ground that he was not
satisfied that the landlord was substantially to blame or that there
had been any unreasonable delay. He further referred to the fact that
if the delay had been after the Civil Procedure Rules had come into
force and if he had been satisfied that the delay was not merely
failure to obey court orders but was due to the landlord delaying in
some way of another, then he would have deprived the landlord of some
interest, and he might even have done so even if it had not been
established that it was the landlord’s fault.
Interest can only be awarded on money being claimed in
proceedings. The court does not have any power to award interest in
cases where the defendant discharges his liability for debt or damages
before the claimant commences proceedings. This is an important fact
to bear in mind by tenants who are liable to pay the cost of work
carried out by the landlord under a covenant allowing him to enter and
carry out remedial work at the tenant’s expense. If the debt is paid
prior to the landlord commencing proceedings, then there will be no
liability or interest. If on the other hand, the debt is paid shortly
after proceedings have been issued, then the landlord will be entitled
to ask for interest to be awarded in relation to the period beginning
on the date when the liability to pay arose. Where the defendant is an
original tenant, the interest may be awarded from the date of the
assignee’s default, even though the original tenant was not aware of
the default at the time. However, the court may be persuaded to adopt
a more realistic approach and award interest only form the date on
which the defendant first became aware of the assignee’s default.
Chapter 3 - The role of the Expert Witness
“The subject of expert witnesses has figured prominently throughout the
consultative process. Apart from discovery it was the subject which
caused most concern…The need to engage experts was a source of
excessive expense, delay and, in some cases, increased complexity
through excessive or inappropriate use of experts.”
Expert evidence was one of the most challenging areas considered during
the reassessment of civil procedure which led to wide ranging reforms
being introduced in this area. The key, as will be discussed in more
detail below, was a re-emphasis on the true duty of the expert to
inform the court rather than to justify the position of the party
paying his fees. Furthermore, when the new CPR came into force, there
was concern at the concept of the single joint expert, the strong
desire to keep expert evidence to a minimum and the requirement to
inform the court of expert availability on allocation of the case.
The CPR have now been operating for a few years, and unsurprisingly
expert evidence in general has generated a high level of case law at
appellate level. Case law tends to show that the role and duties of
experts is evolving, mainly as a result of the court’s emphasis on
proportionality. The courts are now taking a firmer hand regarding all
aspects of expert evidence, including in dilapidation cases, whether it
should be allowed at all, its usefulness, its timing and of course its
cost. Expert evidence will only be allowed if it is really necessary
and if it is, it should not be used more than is necessary.
The reduced use of expert evidence is, however, not to be perceived
as diminishing the value of expert evidence. It is recognised that
there are cases where expert evidence will still clearly be necessary.
Judges cannot be experts in everything. In those cases, the courts
have been careful to warn judges to pay sufficient attention to the
expert evidence before them and to give reasons for preferring one
expert’s evidence to another’s.
The impact of the CPR on expert evidence can be assessed by
reviewing the extent to which some individual rules have been
effectively applied since the introduction of the CPR. These will be
discussed in more detail later in this chapter, although a summary of
the main points include:
The expert’s duty to the Court and not it’s fee paying client. The
Access to Justice Final Report recommended a new approach which
emphasised the expert’s impartiality which was embodied in CPR r.35.3.
As May L.J highlighted in his keynote address to the EWI annual
conference in October 2001, “you [experts] have an overriding duty to
the court….a duty which overrides any obligation to the person from
whom you have received instructions or by whom you are paid. You are
not there to engage in a sparring match with your opposite number.”
The courts have actively upheld this duty by criticising expert
witnesses where they have shown signs of partiality.
Initially, there were concerns that this duty would entail the
appointment of “shadow” experts with whom a party could discuss the
full merits of his case without concern that those discussions could be
stripped of privilege. This does not seem to have materialised before
the courts although anecdotal evidence suggests it is happening to a
certain extent behind the scenes.
CPR r.35.7 introduced the concept of the single joint expert. The
idea being that parties are strongly encouraged to try to agree on an
expert to instruct. Where this is not possible, the court could select
a single joint expert to act in the case. This was not however,
initially welcomed. One of the strong concerns in this area was that
costs would spiral as a result of the need in complex cases to appoint
experts for each party as well as the single joint experts, the costs
of which would be irrecoverable.
In fact, the concept of the single joint expert has been creatively
adapted to suit different matters and courts. The courts have in this
context recognised that, whilst taking into account the possibility of
appointing a single joint expert, there are many multi-track cases
which, by virtue of their complexity and the sums at state, will still
warrant each party having its own experts.
The courts have furthermore enthusiastically taken up the spirit of
written questions to experts provided for by CPR r.35.6, whereby a
party may put to the other side’s expert or a single joint expert,
written questions about his report. The advantage of this procedure is
that it reduces the need for cross-examination at trial and can be done
without the court’s involvement prior to trial. Notably this is an
area of the new procedure which is as yet still underused.
The expert witness in dilapidation cases
The opinion of a properly qualified expert on an issue within his or
her field of expertise can often give a judge invaluable help in
finding a sound answer to problems arising in the course of
litigation. But like all procedural tools expert opinion evidence,
invaluable if properly used can be improperly used and then it can
disfigure the litigious process by causing delay, unnecessary expense
and contamination of what should be independent and objective expert
opinion by considerations of partisan advantage.
An important aim of the CPR is to curb the abuses to which misuse of
expert evidence has given rise in the past while ensuring that the
courts continue to enjoy the help which such evidence alone can give.
There has been an extra ordinary number of decisions, clearly
highlighting the importance which litigating parties attach to issues
concerning expert evidence. Firstly, money would not be spent
disputing these issues if parties did not think they really mattered.
But secondly, the decisions of the courts show that the new rules are
making a demonstrable impact on practices and habits of thought which
were once tolerated but no longer are. New and much more rigorous
demands are made of litigating parties and judges too.
Expert Witness are the only type of witnesses who are allowed to give
opinion evidence when it comes to matters for a court to decide (all
other witnesses are only entitled to give evidence of fact).
Permission from the court would be required prior to the calling of or
submission of any expert evidence and any application for permission
must identify the field of the expertise of the expert to be relied
upon and (if practicable) identify the expert. Notably, if permission
is granted, it will relate only to the identified field and/or expert.
It is normal procedure for the expert to provide his or her evidence by
way of written report and except in a fast-track case, the expert will
under normal circumstances be directed to attend the hearing.
The court will use its case management powers to provide the
appropriate directions under the CPR in relation to expert witness, but
may also give directions in response to an application made by either
party to the proceedings. Part 35 of the CPR provides detailed
provisions in relation to experts and assessors that are expanded upon
in the Practice Direction supplementing Part 35. The purpose of Part
35 is made clear by the following note which appears at the start of
the Practice Direction,
“Part 35 is intended to limit the use of oral expert evidence to
that which is reasonably required. In addition, where possible,
matters requiring expert evidence should be dealt with by a single
expert. Permission of the court is always required either to call an
expert or to put an expert’s report in evidence.”
The case of Field v Leeds City Council provides an interesting
insight to the requirements the courts generally make prior to the
appointment of an expert witness. In this case the county court judge
refused permission to the defendant council who wished to call, as an
expert witness one of its employees, who had, as a member for ten years
of the claims investigation section, been involved in looking into
disrepair matters for the council. The Court of Appeal held that in
principle, there was no objection to a person who is employed by one of
the parties being called as an expert witness by that party, so long as
he was properly qualified. The court noted however, that it was
important that such a person should have full knowledge of the
requirements for an expert to give evidence in court and that he should
be fully familiar with the need for objectivity.
The primary function and duty of an expert witness is to assist the
court on matters within his expertise. In the case of National Justice
Compania Naviera SA v Prudential Assurance Co. Limited Cresswell J set
out seven propositions that are relevant to the performance by expert
witnesses of this duty. These have been quoted in textbooks and
reported judgements over the years and have now largely been subsumed
in the relevant provisions of the CPR. The Royal Institution of
Chartered Surveyors further published a Practice Statement and Guidance
Notes for Surveyors Acting as Expert Witnesses . This statement had
three particularly prominent features. Firstly members of RICS who
accepted an appointment to act as expert witness were required to draw
to the attention of their lay clients, at the time the instructions
were accepted, that the Practice Statement applied. Secondly,
compliance with the Practice Statement was made a requirement of
professional conduct for members of the RICS in performing the function
of an expert witness, so that a failure to comply would amount to a
disciplinary offence. Thirdly, it required a member, in the body of any
expert report which he compiled in the capacity of a witness, to set
out his duties under the Practice Statement and to confirm that he had
complied with them. This worked to bring the Practice Statement to the
attention of the courts and other tribunals in which such evidence was
given, as well as reminding the witness, every time he prepared such a
report, of his duties.
Similarly, the provisions incorporated in CPR r.35.10(1) now emphasise
that the primary duty of the expert witness is to the court an not to
his or her client, and require an expert’s report to comply with the
requirements set out in any relevant Practice Direction.
The Practice Direction Experts and Assessors sets out detailed
provisions to regulate the form and content of expert’s reports. In
particular, it requires any such report to be verified by a statement
of truth confirming the expert believes the facts stated in his report
to be true and that his or her opinions are correct. Furthermore, CPR
r.35.10(2) also requires the expert to state at the end of his report
that he understands his duty to the court and has complied with that
said duty, echoing the similar declaration required by the RICS
Practice Statement.
All reports are to state the substance of all material instructions,
whether written or oral, on the basis of which the report was
written. Furthermore, the instructions provided are not to be
privileged against disclosure. Notably it is also provided that the
court will not order disclosure of any specific document or allow any
questioning in court by the other party in relation to those
instructions, unless the court has reasonable grounds to consider that
the statement of the substance of the instructions is inaccurate or
incomplete.
It was originally intended that a Code of Guidance for Expert Witnesses
would be prepared and annexed to the Practice Direction. However,
aster a long delay at the time when the CPR were being prepared, the
Master of the Rolls authorised in 2001, the publication of the “Code of
Guidance on Expert Evidence: A Guide for experts and those instructing
them for the purpose of court proceedings.” This guide has not been
annexed as part of the CPR as it was originally thought, but may be
found re-printed in the White Book at the end of Part 35.
Single joint experts
An important innovation found within the CPR is the court’s power
under r.35.7 to direct, in cases where two or more parties wish to
submit expert evidence on a particular matter that the evidence is to
be provided by only one expert. Parties who wish to submit expert
evidence are referred to as “the instructing parties”. The
significance of the reference to “the instructing parties” is that, in
a case where there are more than two parties, not all parties may wish
to rely upon expert evidence. Those parties which do not wish to do
so, are not required to instruct the joint expert and may challenge his
evidence in the same way as they could challenge any other expert
evidence put before the court, but they will not, of course, have any
expert evidence f their own upon which they can rely. The instructing
parties may agree the identity of the single joint expert although in
instances where they cannot agree, the court may select an expert from
a pre-prepared list prepared by the instructing parties or direct that
the expert be selected in some other manner. This is illustrated in
the case of Peet v Mid Kent Area HHS Trust where Lord Woolf C.J
stated, “as we will see when we come to the framework which is provided
by the Civil Procedure Rules, the Rules permit the Court to require the
parties to use a single expert. This is not a matter of choice for the
parties. In the absence of special circumstances I consider that the
appropriate way that the power should be exercised is to require a
single expert rather than an expert for each party. It is only by so
doing that control can be exercised over the costs involved…In relation
to Part 35.7 I would emphasise that the power of the court to direct
that the evidence be given by a single joint expert is unrestricted.
The court has a wide discretion and that discretion has to be used in
order to further the overriding principles set out in Part 1 of CPR.”
Making reference to the framework as provided by the Rules, Lord Woolf
stressed that the said rules were designed to provide a flexible
framework, and that there would always be cases wherein special
treatment is required due to the particular issues that arise
thereunder. Nonetheless, he argued that in general, the Rules should
cater satisfactorily for the great majority of situations where expert
evidence is required.
Where a direction for a single joint expert has been made, r.35.8
allows each instructing party to give instructions to the expert, a
copy of which must be sent to the other instructing parties. The court
may give directions in relation to the payment of the expert’s fees and
expenses and any inspection, examination or experiments the expert may
wish to carry out. Furthermore, the court may also limit the amount
that can be paid by way of fees and expenses to the expert, prior to
the instruction of the latter, and order the instructing parties to pay
that amount into court. Importantly, unless the court directs
otherwise, the instructing parties will be jointly and severally liable
for the payment of the expert’s fees and expenses.
Paragraph 5 of Practice Statement Experts and Assessors, provides
that in instances where the court has made a direction for a single
joint expert but there are a number of disciplines relevant to the
particular issue, a “leading expert in the dominant discipline” should
be identified as the single expert and should prepare the general part
of the report and be responsible for annexing or incorporating the
contents of any reports from experts in other disciplines. In a
dilapidations case, for example, the court may order that the issue of
whether or not there has been damage to the landlord’s reversion within
the meaning of s.18 of the Landlord and Tenant Act 1927 and of the
amount of any such diminution should be the subject of a report by a
single expert and a valuation surveyor might be designated as the
“leading expert”, who would then in turn rely upon the opinion of, for
example, an expert as to market conditions prevailing at the relevant
time. Similarly, if the court had directed that a single building
surveyor should present evidence as to what remedial works were
required so as to comply with the repairing obligations of the lease,
he might be designated as the “leading expert” who would incorporate in
his report the findings of various specialists dealing with mechanical
and electrical services, lifts and the electrical installations in the
building.
The CPR and Practice Directions do not provide explicit guidance as to
what is to happen one the single joint expert has reported. It has
been left to a number of decided cases to clarify the procedures. In
Peet v Mid Kent Area Healthcare NHS Trust Lord Woolf quoted a passage
from the White Book which stated, “If a single joint expert is called
to give oral evidence at trial it is submitted, although the rule and
the Practice Direction do not make this clear, that both parties will
have the opportunity to cross-examine him or her, but with a degree of
restraint given that the expert has been instructed by the parties.”
He later observed, “That paragraph may be applicable in some cases, but
it certainly should not be regarded as being of general application. I
summarise my reasons for so saying. The starting point is: unless
there is reason for not having a single expert, there should only be a
single expert. If there is no reason which justifies more evidence
that that from a single expert on any particular topic, then again in
the normal way the report prepared by the single expert should be the
evidence in the case on the issues covered by the expert’s report. In
the normal way, therefore, there should be no need for that report to
be amplified or tested by cross-examination. If it needs
amplification, or if it should be subject to cross-examination, the
court has a discretion to allow that to happen. The court may permit
that to happen either prior to the hearing or at the hearing. But the
assumption should be that the single joint expert’s report is the
evidence. Any amplification or cross-examination should be restricted
as far as possible. Equally, where the parties agree that there should
be a single joint expert, and a single joint expert produces a report,
it is possible for the court to permit a party to instruct his or her
own expert and for the expert to be called at the hearing. However,
there must be good reason for that course to be adopted….if there is an
issue which requires cross-examination, or requires additional
evidence, that is one thing. But the court should seek to avoid that
situation arising, otherwise the objectives of having a single expert
will in many situations be defeated.”
The Court of Appeal in the case of Popek v National Westminster Bank
Plc applied the above decision, where the court upheld a decision by
the judge to strike out a claim, where the single joint expert’s report
showed that there had been no breach of duty on the part of the
defendant. It was held that the judge had not been in error in
depriving the claimant of the opportunity of putting his version of
facts to the expert by way of cross examination. In that case however,
it is to be noted that the claimant had not taken the opportunity at an
earlier stage to put his disputed version in questions to the single
joint expert.
This approach contrasts with that held in the case of Layland v
Fairview New Homes Plc. In this case, a valuer had been appointed as
a single joint expert, so as to assess the amount of diminution in the
value of a flat the claimants claimed had suffered as a result of the
grant of planning permission to build an incinerator and power plant
close by. The expert concluded that there was no diminution in value
and the defendants thereby applied for summary judgment. Neuberger J
held that in order to resist summary judgment dismissing the claim
under Part 24, the claimants had to establish that they had a real
prospect of successfully challenging the single joint expert’s
conclusion. Provided there was a prospect of the expert through
cross-examination, or the court, through submissions, being persuaded
to a different conclusion than that supported by the single joint
expert’s report, the claim could not be dismissed on the basis of the
expert’s view. In light of the fact there were some points which could
be put to the expert and accepted by him or by the court and since the
court could not properly reject those points without hearing how the
single joint expert dealt with them, it would not be right to grant
summary judgment dismissing the claim. Despite the fact the claimants’
case on diminution seemed weak and speculative and even if successful
was not likely to result in a large award, it could not fairly be said
to stand no realistic chance of success.
In the case of Pattison v Cosgrove a single joint expert was
appointed in a boundary dispute to report on various issues including
the position of the boundary and whether some excavation works had
undermined certain structures. Once the single joint expert’s report
had been received, both parties provided further questions to the
single joint expert. Subsequently one of the parties applied to the
court for permission to call another expert and this was refused. The
application was however, allowed on appeal where Neuberger J stated,
“although it would be wrong to pretend that this is an exhaustive list,
the factors to be taken into account when considering an application to
permit a further expert to be called are these. First, the nature of
the issue or issues; secondly, the number of issues between the
parties; thirdly the reason the new expert is wanted; fourthly, the
amount at stake and, if it is not purely money, the nature of the
issues at stake and their importance; fifthly, the effect of permitting
one party to call further expert evidence on the conduct of the trial;
sixthly, the delay, if any, in making the application; seventhly, any
delay that the instructing and calling of the new expert will cause;
eighthly, any other special features of the case; and, finally and in a
sense all embracing, the overall justice to the parties in the context
of the litigation.”
Single joint experts are not appointed by the court so as to advise it
or to present evidence to it. Accordingly, the report produced by the
expert witness is evidence available to each of the instructing
parties, which that party may or may not decide to put in as evidence.
The party who puts in the evidence would then be bound by it and could
not dispute it by, for example, cross-examining the single joint
expert. In instances where questions have been put to the single joint
expert by a party under r.35.6, the expert’s answers will be treated as
part of his report by virtue of r.35.6(3).
It is therefore likely that, in a typical case, where there has been a
direction for a single joint expert, the report will consist of the
expert’s original report together with answers to such questions as the
parties have chosen to put to him. If one of the instructing parties
is entirely content with the result of this process, he will put the
report in evidence and make it part of his case. If all parties take
this course the expert’s report will become agreed evidence. However,
if one of the instructing parties in not happy with the report of the
single joint expert (including relies to any questions which that party
has submitted) that party may decide not to put the report in
evidence. In this case however, the instructing party may be faced
with a problem in that he has no evidence of his own on this particular
issue, unless he is able to persuade the court that, notwithstanding
the fact that a direction for a single joint expert has been made, it
would be appropriate for him to have permission to instruct his own
expert dealing with that particular issue. A party that has not put
the report of the single joint expert in evidence as part of his case
(irrelevant of whether it is one of the “instructing parties”) appears
to be entitled to require the single joint expert to give evidence, and
to cross-examine him. Despite the fact that party may have the benefit
of advice from his own expert in the relevant discipline on that
particular issue, which could form the basis for cross-examination,
that expert could not be called (unless the court has given
permission).
It remains unclear how often the court will make a direction for a
single joint expert in dilapidations cases, whether such experts will
be directed on issues of what breaches exist, what remedial work is
required, what the proper pricing of the work is, what damage (if any)
has been caused by the landlord’s reversion, or in relation to all
those issues. It seems unlikely that joint experts will be frequently
appointed in dilapidations claims, at least in major claims in the
Technology and Construction Court.
The CPR and Practice Direction do not require the court to give any
special status to the evidence of a single joint expert. In practice,
the opinion of a single joint expert, who has been chosen by more than
one party (or by some process directed by the court), instructed by
those parties and having been subjected to questioning by those
parties, is likely to be considered by the court as being especially
authoritative, quite apart from the fact, in most cases where a joint
expert has been appointed, there will be no other expert evidence on
that particular issue.
Written questions to experts
Posing written questions to experts is regulated by CPR, r.35.6, which
allows for each party to put to an expert instructed by another party
or to a single joint expert written questions in relation to his
report. These questions must be made only once. They must be made
within 28 days of service of the expert’s report and must only be for
the purpose of clarifying the report (unless the court grants
permission or the other party agrees).
Importantly, the answers to any of the questions posed, become part
of the evidence of the expert who has provided the answers, meaning
they become part of the evidence that is being relied upon by the party
who has instructed the expert. Significantly, the party who has asked
the question can (if the answer provided by the expert supports their
case) accept that part of the evidence, but also retains the right (in
instances where the answers do not support their case) to cross-examine
the expert upon it and to call evidence to contradict or undermine the
answer given (notably this may only be done to the extent that the
directions given allow).
It therefore seems as though the right to ask questions can usefully be
used both (a) to obtain the expert’s confirmation that he accepts
certain points upon which the questioning party wishes to rely but also
(b) to expose for cross-examination a view of the expert which is
thought to be vulnerable to attack. The power to put such questions
may also draw out useful background material, including whether there
are any particular matters upon which the expert has relied in order to
support particular conclusions already stated in his report.
It is important to note, that for tactical reasons, the party who puts
the questions to the expert, will have to consider to what extent the
points which might be raised can be more effectively dealt with in
cross-examination and to what extent they wish the other party’s expert
to set out in advance of cross-examination his answer to their
question.
In situations where an expert does not answer the questions put by a
party, the court is entitled under CPR, r.35.6(4) to order that the
party who instructed the expert may not rely upon his evidence and/or
that the party may not recover the fees and expenses of that expert
from any other party.
Discussions between experts
By virtue of CPR, r.35.12, the court may at any stage of the
proceedings, direct the experts to enter into a discussion for the
purpose of requiring them to firstly identify the issues and secondly,
where possible, to reach an agreement on an issue. This is a similar
power to that previously conferred on the court by RSC O.38, r.38 and
accords with the practice that has evolved in the Official Referees’
courts. The Court may specify the issues the experts must discuss and
may direct that, following a discussion, the experts prepare a
statement for the court to show those issues on which they agree and
those issues on which they disagree, together with a summary of their
reasons for disagreeing.
Despite the fact the previous RSC O.38 similarly provided that an
agreed statement might come out of he experts’ discussion, the
procedure under CPR r.35 is more prescriptive, and conforms to the
principle that the experts’ overriding duty is to the court. The case
of Robin Ellis Limited v Malwright Limited decided under the former
Rules of the Supreme Court illustrates this point. In this instance,
the Official Referee, Judge Bowser Q.C highlighted the fact that it was
not for the parties to tell the experts what opinions they were allowed
to hold, and that the duty owed to the court by the experts was to
express in their agreement the views which they themselves honestly
held.
Previously, the procedures allowing experts to meet have shown
themselves to be useful and the new rule should continue to do so.
Experts will sometimes be in a position where they are able to reach an
agreement to such an extent that their attendance at trial can be
dispensed with. This is illustrated in instances where the respective
building surveyors may be able to agree on what work should have been
done and what it would have cost, leaving the question of damage to the
reversion as the only live issue at trial. Even in cases where
complete agreement on a substantive issue is not possible, the experts
will often be in a position to reach agreement in relation to matters
which would otherwise take up time at trial. For example, valuers
should in most cases be able to agree on matters such as floor areas
and the details of their respective comparables, and building surveyors
who differ on what work is required should nonetheless be able to agree
on the cost of the work for which each contends.
Furthermore, in echoing the previous provision to the effect that
the meeting between experts should be on a “without prejudice” basis,
CPR, r.35.12(4) provides that the content of the discussions between
experts shall not be referred to at the trial unless the parties agree
to this.
Whist discussing, experts are to make a proper attempt to identify
and narrow the issues on which they differ. Importantly, if an expert
is persuaded by his opposite number that his view on a particular issue
is wrong, he will not be able to write a report expressing his original
view and ought to instead agree that matter in the statement for the
court. Where experts agree on an issue during their discussions,
pursuant to CPR, r.35.12(5), the agreement shall not be binding on the
parties unless the parties expressly agree to be bound by the
agreement. This does not however, release the expert from his duty to
the court as to the truthfulness of his evidence which means that in
practice, where an expert has reached agreement with his opposite
number the party instructing him will normally have no option but to
agree its inclusion in the statement.
The rule clearly envisages an attempt in good faith by both experts to
discuss the issues, to narrow the differences between them, and to
record what common ground exists. For example, an expert would not be
complying with the rule if he or she attended discussions and informed
the opposite number that he or she has no instructions to discuss
anything but is prepared to listen to what is said. In the same
manner, a discussion meeting should not be utilised to discuss
settlement of the action since there will then be a danger that the
expert will confuse his duty to the court with his duty to his client
to obtain the best possible settlement.
The court has the power to direct discussions at any stage of the
proceedings, although the most advantageous time for such discussions
will normally be before reports are exchanged so as to allow for the
reports to be written on the basis of the areas of agreement and
disagreement identified at the meeting. Sometimes, a further meeting
after exchange of reports may be useful if the result of exchange is
further to clarify the nature of the matters in difference.
Content of experts’ reports
The Practice Direction to rule 35 requires that the report should be
addressed to the court and not to the party from whom the expert has
received his instructions. Furthermore, the report should give details
of the expert’s qualifications, as well as details of any literature or
other material the expert has relied on in making the report. In
accordance with CPR, r.35.12 and as referred to previously in this
essay, there should also be the inclusion of an appropriate statement
of truth in the body of the expert’s report. Paragraph 1.2(5) provides
that, where “there is a range of opinion on the matters dealt with in
the report”, the report should summarise the range of opinion, and give
reason for the expert’s own opinion. This appears to be addressed to
issues of practice or principle on which there is a known and
acknowledged range of opinion between experts in the field. It does
not mean that on every occasion on which an expert things that another
expert might disagree with him on a particular point, he is required to
say so and go on to say what view that other expert might hold.
Subject to these particular provisions, the contents of an expert’s
report varies from case to case. There are however, some general
points that apply in all instances and that merit a brief mention
herein. Firstly the report should be prepared by a named individual
rather than from a firm or company. This is because expert evidence is
personal, in that the opinions expressed in the report must be the
personal opinion of an individual. After all it may be that that
particular individual is later called upon to give oral evidence and be
cross-examined on his evidence. Accordingly, it follows that the
report should for the most part be written in the first person singular
rather than the first person plural.
Secondly, the report must demonstrate the witnesses’ credentials to
be considered an expert and, in order to explain the nature of his
particular field of expertise, the report should contain a statement
not merely of his formal qualifications but also something about his
career and the nature of his practical experience.
Thirdly, in dilapidations cases, the expert’s evidence will almost
always be based on what he has observed on inspecting the premises, as
well as other matters. Accordingly, the expert should give the dates
of those inspections and, where appropriate, also explain the reason
for his visit.
Fourthly, in some instances, the expert may wish to make particular
points about the physical nature of the subject-mater of his
inspection. He will have to decide whether the best means of conveying
this to the court is by a verbal description or by reference to
location plans, or photographs or a combination of some or all of
these.
Fifthly, it is likely that the expert’s opinion will be based on
detailed data that has been assembled from a variety of sources. So
that the court may understand this, the rule upon the admissibility of
some parts of the evidence if necessary, it should be made clear in the
body of the report what is the source and nature of the information
that is being relied upon. Sometimes the expert will simply be setting
out or referring to something of which he has first-had knowledge, such
as a schedule of dilapidations referred to by the building surveyor who
drew it up. Sometimes the expert will be referring to information of a
factual nature supplied by third parties. An example of this is the
fact the expert valuer may refer to details of comparable transactions
supplied to him by other agents. Sometimes the data will e of a more
generalised nature, such as statistical surveys, analyses of market
trends or indices of building costs.
Finally, after having demonstrated the material, factual and
otherwise, upon which his evidence is based, the expert should clearly
set out the conclusions that have been reached. The expert must set
out in as much detail as he considers appropriate the method and line
of reasoning which has led him to his conclusions.
Whilst writing his report, the expert must bear in mind that he is
required to be objective and he must express his honest opinion.
Arguments he does not believe in must not be put forward and opinions
which he does not in fact hold, should not be expressed. In instances
where there is a point that can fairly be made against him, he should
acknowledge it and explain why it does not cause him to change his
views. In all, he should aim for a balanced and fair assessment of the
subject matter in his report.
Human Rights and the Expert Witness
The Human Rights Act 1998 also has a potentially significant impact
on the rules governing expert evidence. Firstly, under CPR r.35.4, the
court has total control over the use of expert evidence and should
limit such evidence to that which is necessary to resolve the
proceedings justly. This power lends itself to allegations that
Article 6 of the European Convention on Human Rights has been breached,
in that evidential restrictions have denied a party a fair trial.
Secondly, it may be argued that the appointment of a single joint
expert is an infringement of parties’ rights to a fair trial, although
this has yet to be tested. Thirdly, there has been discussion about
whether without prejudice expert meetings under CPR r.35.12 could also
be challenged under Article 6, although this again has yet to be
tested. It is perhaps surprising that more challenges have not been
made to Part 35 on the basis of Article 6. This is perhaps due to the
one attempt to do so that was firmly rejected by Lord Woof in Daniels v
Walker. In this case, the issue before the Court of Appeal was of
some significance as to the approach which judges should adopt when a
single joint expert has been instructed and where one side is unhappy
with that report. The facts arose from an accident in which the
claimant was involved as a child. The single issue before the Court of
Appeal was the nature of the care which the claimant would require in
the future. On receipt of the report from the joint expert, the
defendant was concerned at the extent of the care regime recommended by
the expert and sought to obtain a further care report from another
expert. The appellants advanced two separate arguments before the
Court of Appeal, firstly they raised an argument based on the CPR and
secondly they raised an argument based on the Human Rights Act 1998 and
the European Convention on Human Rights (albeit that the 1998 Act was
not in force at the relevant time).
As to the CPR argument, the court referred to the overriding
objective of the CPR r.35.1 (which places a duty on the court to
restrict expert evidence) and CPR r.35.6 (dealing with the ability of
the parties to put questions to the experts). The court also referred
to CPR r.35.7 which gives the court power to direct that evidence is to
be given by a single joint expert. Having considered the relevant
rules, the Court of Appeal said that the fact that a party has agreed
to instruct a joint expert does not prevent that party being allowed
facilities to obtain a report from another expert, or, if appropriate,
to rely on the evidence of another expert. The Court of Appeal added
that in substantial cases, such as this, the correct approach is to
regard the instruction of an expert jointly by the parties as the first
step in obtaining expert evidence on a particular issue. The court
added that it is to be hoped that in the majority of cases it will not
only be the first step but the last step. However, if having obtained
a joint expert’s report, a party, for reasons which are not fanciful,
wishes to obtain further information before making a decision as to
whether or not there is a particular part (or possibly the whole) of
the expert’s report which he or she should, subject to the discretion
of the court, be permitted to obtain that evidence.
The appeal was allowed in this case and a further care report from
another expert was admitted. However, the Court of Appeal noted that
this would not be the case where it is suggested that the claimant
would be unduly distressed, or anything of that nature, by the
additional examination.
As to the Human Rights arguments, the defendant argued that having
regard to the provisions of Article 6 of the European Convention on
Human Rights, a refusal of the defendant’s wish to instruct a second
expert would conflict with Article 6 because it amounted either to
baring the whole claim of the defendant or barring an essential part of
that claim.
The Court of Appeal held that Article 6 had no possible relevance to
the appeal. The court said that, even if the Act had been in force, it
would be highly undesirable if the consideration of case management
issues was made more complex by the injection into them of Article 6
style arguments. The Court of Appeal said that it hoped that judges
would be robust in resisting any attempt to introduce such arguments.
It seems that the biggest impact the 1998 Act has had on expert
witnesses is in relation to the bias issues. These occur where there is
reason to believe that an expert may be biased towards one party and
the result of successful allegations could be that evidence is
excluded, or given less weight. This may in some instances apply to
dilapidation matters generally, and is likely to damage a party’s
case. Accordingly, steps should be taken in all cases to avoid any
hint of bias.
Chapter 4 – Alternative Dispute Resolution and Dilapidation claims
The introduction of the CPR has meant that it is more likely that
dilapidation claims will end up being resolved by agreement rather than
by litigation. It is therefore important at this stage, to consider
the options available to those who wish to resolve dilapidation
disputes without entering into litigation.
Arbitration
The first alternative to be considered is that of arbitration.
Arbitration is based on the agreement of the parties and unlike
litigation, has limited intervention by the state. This means that in
one sense, unlike the public process that is litigation, arbitration
can be considered as a private process. Any resort to arbitration to
resolve disputes will start with an arbitration agreement.
In dilapidation cases, such an agreement may be found in a clause in
the lease that gives either party the right to refer to arbitration if
any disputes arise under the lease. However, such clauses are, in
practice rarely to be found in leases in a form wide enough to embrace
the typical dilapidations dispute (as opposed to a more limited
arbitration clause aimed at a particular subject-matter such as service
charges, where arbitration clauses are somewhat more common, or rent
review, where provision for arbitration by a surveyor is widespread).
Accordingly, in the absence of such a clause, arbitration will only be
possible if the parties agree that for the purposes of their immediate
dispute, it is to be referred to arbitration. If the agreement is in
writing, as required by s.5 of the 1996 Act, it will be enforceable by
either party, and if the other party seeks to resort to litigation
instead, a stay can be obtained from the court under s.9 of the 1996
Act.
The person chosen as the arbitrator should be qualified to
understand the issues that arise in the particular disputed referred to
him. It is not normal procedure for an arbitration clause in a lease
to provide for a named individual arbitrator. Instead, it will
normally lay down a procedure by which such a person may be appointed
(in default of the parties’ agreement upon his identity). In a clause
in a lease that is specifically aimed at dilapidations disputes, the
President of the Royal Institution of Chartered Surveyors or of the Law
Society is likely to be named as the person to make appointments. If
however, there are no appointment procedures outlined within the lease,
or of for some reason those that are set out fail to operate, the 1996
Act provides a “fall back” appointment procedure. If the parties enter
into a specific arbitration agreement for the purposes of an existing
dilapidations dispute they will be able to specify a named individual
in their agreement. Alternatively, they may invoke the appointment
procedures of the RICS or the Law Society or some other appointing
institution or rely upon appointment by the court.
It is always preferable to obtain an appointment by specific agreement,
as this would give the parties the maximum control over the identity of
the person who is to decide their dispute. Once an arbitrator has been
appointed, he or she will give directions for a speedy and cost
effective resolution of the dispute under s.34 of the 1996 Act. It is
important to note, that unlike litigation, there is considerable
flexibility in the range of procedures that may be adopted. For
example the arbitration may be conducted wholly in writing or there may
be an oral hearing. Furthermore, the arbitrator may be given power to
take the initiative in ascertaining the facts and the law. The strict
rules of evidence may or may not apply and under s.37, the arbitrator
may appoint a legal or other assessor to assist him.
Procedural matters may be agreed between the parties. If they are
unable to do so, these may be determined by the arbitrator in
accordance with hi general duty under s.33 to act fairly and
impartially between the parties, allowing each party a reasonable
opportunity to put forward his case and dealing with that of his
opponent, and adopting procedures suitable t the circumstances of the
particular case, avoiding unnecessary delay and expense, so as to
provide a fair means for the resolution of the matter falling to be
determined. This may resemble a superficial resemblance to litigation
procedures under the CPR, but the important difference is that the
parties control most aspects of arbitration proceedings (except where
there is disagreement, in which case the arbitrator decides) while
under the CPR the court’s case management powers override the wishes of
the parties as to how the proceedings should progress.
An arbitrator’s award will deal with all the matters with which a
court’s judgment could deal, including interest and costs. It is
enforceable in the same way as a court judgment and unless the parties
agree otherwise, will contain reasons for the decision.
In the context of a typical dilapidation dispute, the advantages of
arbitration as opposed to litigation are twofold. Firstly the right to
choose a specific person to decide the dispute enables the parties to
have the matters resolved by a person from a relevant discipline who is
not necessarily a lawyer and who may be thought for some particular
reason to be a more suitable tribunal than a judge. Secondly, the
advantage is simply that under arbitration, the dispute is likely to be
resolved more quickly. The reason for this is not due to the fact the
arbitrator is, in general terms, at the parties’ disposal, whereas a
judge has public duties towards other litigants resulting in a
comparable case in court being unlikely to be tried within the
timescale which could be achieved at arbitration.
Arbitration may also provide a more flexible range of procedures,
especially the possibility of avoiding an oral hearing. Having said
that, the improved procedures brought in by the CPR, allied to the
special techniques evolved by the Technology and Construction Court,
make the difference between the relevant procedures less marked in
dilapidation dispute instances, than in other litigation.
A disadvantage of arbitration is also that the parties will be put
to the additional cost of paying the arbitrator’s fee, as well as any
assessors whom he may appoint. In a dilapidations case, where the
complexity of the issues may sometimes require a lot of time to be
devoted by the arbitrator and assessor, the additional costs may be
quite considerable. Furthermore, in cases where a lengthy hearing is
involved, the costs of hiring a suitable venue must also be borne in
mind. Notably in such instances as those described, court fees payable
in respect of a comparable dispute being resolved by litigation are
relatively insignificant.
Expert determination
A second process by which litigation in dilapidation cases may be
avoided is that of expert determination. Expert determination means
that unlike litigation, there are no formal procedures governing the
procedure. Furthermore, an expert essentially decides the matter
referred to him according to his own knowledge and experience and not
the evidence put before him by the parties.
Expert determination may be less suitable than arbitration in
dilapidation cases where substantial issues and sums of money are
involved. This is because such a dispute will inevitably be so complex
that it cannot generally be safely entrusted to the decision of a third
party without the benefit of hearing and weighing and adjudicating upon
the various points put by the opposing parties. On the other hand,
expert determination may be well suited to disputes where the issues
are straight forward or where the sums at stake are low or of
particular issues which the parties cannot agree and the resolution of
which is likely to facilitate an overall settlement of the entire
claim. The Dispute Resolution Service of the Royal Institution of
Chartered Surveyors is launching a scheme to facilitate determination
of dilapidations disputes by a Chartered Surveyor appointed either as
an arbitrator or as an expert, depending upon whichever the parties
think is most appropriate in their particular instance. In appropriate
cases, this will be a speedy and cost effective alternative to
litigation either for entire dilapidation disputes or for particular
issues which the parties cannot agree.
Mediation
A third alternative process to be considered is that of mediation.
CPR Part 26 and the Practice Direction on Case Management make
provision for a stay of proceedings to allow for settlement of the
case. Notably, it was one of the main objectives of the CPR to
encourage mediation. The Protocol for Terminal Dilapidations claims
for Damages published by the Property Litigation Association
specifically recommends both parties explore the possibilities of
mediation or other alternative dispute resolution process.
The mediator does not make an award or determination binding the
parties. Instead his role is purely to facilitate the settlement by
the parties of their dispute and if mediation is successful, it will
result in a compromise between the parties that is legally binding upon
them in the same was as contract. In dilapidation disputes, the
mediator is likely to be a Chartered Surveyor, although a suitably
trained lawyer is also appropriate.
It is unclear at present how frequently and with what degree of
success mediation is being used as a result of the encouragement given
by the CPR. Mediation seems well suited to the sorts of issues arising
out of dilapidation claims as they are usually a number of interlocking
issues as well as a number of disputed points which are of commercial
importance to the parties but which are not necessarily susceptible to
resolution through the ordinary litigation process.
Early Neutral Evaluation
A fourth and final alternative is that of Early Neutral Evaluation.
Early Neutral Evaluation is referred to both in the Admiralty &
Commercial Courts Guide, and in dilapidation matters in the Technology
and Construction Court Guide. What is envisaged in the Commercial
Court, is a discussion between the advocates and a judge, from which it
appears to them that and Early Neutral Evaluation is “likely to assist
in the resolution of the dispute or of particular issues”, in which
case it will, if both parties agree, be referred to a judge who is to
provide a “without prejudice non-binding early neutral evaluation”.
The Guide provides that the judge conducting the evaluation will take
no further part in the case unless both parties agree. Similar
procedures are set out in paragraph 6.5 of the Technology and
Construction Court Guide.
The intention of this process is to allow both parties to learn what
are the strengths and weaknesses of their respective arguments and to
see the reaction of a judge of the court which will try the dispute if
it does in fact go to court. It is hoped this process will help the
parties narrow the issues, or focus their arguments, or to accept that
the result of a full trial is not likely to be much different from that
indicated by the evaluation, and to compromise their differences
accordingly. It is not thought that this particular alternative
dispute resolution procedure has to date been much used in
dilapidations claims, but the procedure would seem to be one which, in
principle, might be usefully applied in such cases.
Conclusion
So have the changes brought in by the CPR been effective? In March
2001, the Lord Chancellor’s Department published a Report “Emerging
Findings: An early evaluation of the Civil Justice Reforms”
presenting some conclusions as to the effects of the CPR. The report
evaluates whether certain goals of the new procedures have been met,
for example, the goals that litigation will be avoided wherever
possible, will be less adversarial and less complex and more
co-operative, and that parties of limited financial means will be able
to conduct litigation on a more equal footing.
The key findings were as follows:
1. Overall, there has been a drop in the number of claims issued, in
particular in the types of claims where the CPR have been introduced
2. Anecdotal evidence suggests pre-action protocols are working well to
promote settlement before issue and reducing the number of ill-founded
claims
3. There is evidence showing that settlements at the door of the court
are now fewer and that settlements before the hearing day have
increased. Part 36 has been welcomed by all interested groups as a
means of resolving claims more quickly. Despite the fact offers to
settle can be made at any time during proceedings, there is a
widespread belief that they are used in the early stages of a claim so
that a trial may be avoided.
4. The number of cases using Alternative Dispute Resolution has
increased, suggesting that since the introduction of the Civil
Procedure Rules, parties are more likely to try alternative means of
settling claims.
5. The use of single joint experts seems to have worked without
problems. It is likely that their use has contributed to a less
adversarial culture, earlier settlement and may have cut costs.
6. Case Management Conferences are a key factor in making litigation less complex, and appear to have been a success.
7. The time between issue and hearing for those cases that go to trial
has fallen. The time between issue and hearing for small claims has
risen since the introduction of the Civil Procedure Rules
8. The number of appeals in the course of proceedings appears to have
fallen sharply. A definitive view on costs is however, difficult to
establish. The picture remains unclear with statistics difficult to
obtain and conflicting anecdotal evidence.
9. The views of litigants in person are difficult to obtain in light of
the fact they tend to use the system only once. Whilst research is
being undertaken to assess their views, anecdotally it appears that the
courts are providing the assistance required.
10. Sources external to the Lord Chancellor’s Department show that,
with one or two exceptions, the civil justice reforms have been well
received overall.
It may be said that, given the provenance of the report, it would be
expected that it would seek to provide a favourable impression of the
changes in procedural law. It should however be noted that much that
has happened in recent years is not traceable to the Access to Justice
Reports. As a longitudinal study, the report is long on anecdote and
short on robust evidence (largely because evidence of the performance
of the civil justice system prior to the CPR coming into effect is
slender). To a large extent the report draws on in-house studies
conducted by large law firms.
In some respects, the report understates the success of certain
aspects of the new rules and, in others, overstates the success.
Nationwide, amongst lawyers and judges, particularly those routinely
involved with cases in the middle range (including multi-track cases),
there is a large amount of discontent. The criticism is not directed
at the objectives of the new civil justice system, but rather at a
perceived lack of resources sufficient to make the system work
properly. Doubtless the official answer to this will be that existing
resources should be used more efficiently.
The use of resources is at the centre of the Lord Chancellor’s
Department Consultation Paper on “Modernising the Civil Courts”
published in 2001. This paper claims to indicate how the Court Service
“will become a modern customer-focused organisation, providing
excellent services, by the effective use of technology and through
significant re-organisation.” The key components of this new vision
which the Court Service has for its future fore are said to be a new
way of managing the civil justice system, new ways of serving our
customers, and a new way of handling cases and supporting our judges
and staff. To an extent, the Modernising the Civil Courts Programme is
a response to the recommendations made by Lord Woolf in his Reports as
to the crucial role of information technology in implementing the civil
justice reforms he proposed. Those concerned with the lack of
resources presently available to the civil justice system will need to
be persuaded that the objectives of the Programme are not to reduce
further the number of High Court and County court offices throughout
the jurisdiction and the number of staff serving in them. A
consequence of the sharp drop in the number of civil claims being
started since the introduction of the civil justice reforms came into
effect is a serious reduction in the income from court fees. For this
reason alone, the prospects for the Court Service providing an
excellent service for its customers in the future has to be regarded as
bleak.
In relation to dilapidation claims, it is arguable that it is not
only the smooth running of the litigation process that is necessary,
but also some reform in the law itself. Dilapidation law is derived
mainly from the common law and like many other areas of English law it
has developed rather sporadically and on a case by case basis. Few
statutes of universal application exist, and those that do have been
enacted as a response to perceived unfairness of the common law in a
particular area. Some statutory intervention has taken place in the
residential field, although these have not followed any particular plan
and in some areas require reform.
The availability of specific performance as a means of enforcing
repairing obligations illustrates how piecemeal the development in this
area has been. Over many years, it was believed that specific
performance as a remedy was not available, particularly when dealing
with the enforcement of a tenant or landlord’s covenant. It was only
in 1974 that an order for specific performance of a landlord’s covenant
in favour of a tenant of a dwelling was finally conferred by statute.
Despite this fact, some uncertainty remained regarding the availability
of the remedy in relation to a tenant’s covenant. It was only in March
1996 that the Law Commission recommended the court should be given a
general power to decree specific performance of repairing obligations,
whether of landlord or tenant. This recommendation has not yet been
implemented, although in 1998 the High Court decided at first instance
that power to order specific performance of a tenant’s repairing
covenant exists anyway.
The piecemeal development of the law has been matched by a deeply
conservative approach to the drafting of dilapidations obligations in
leases There are of course exceptions to the rule, but most draftsmen
have tended to stick to the old tried and tested formulae including the
traditional obligation to repair and keep in repair. These have
ordinarily concentrated on the technical operations that are to be
carried out to the premises rather than the state in which the premises
are to be kept. This has meant that there are some cases where the
relevant obligation has been held not to have been broken even though
the premises are clearly unusable. This means that in a number of
areas, the law of dilapidations does not provide the comprehensive
solution to modern problems which a more structured and radical
approach might provide.
In March 1996 the Law Commission published its report Landlord and
Tenant: Responsibility for the State and Condition of Property. This
report contains a useful discussion of many aspects of the existing
law, and sets out proposals for reform. The introduction concludes
that there are some serious short comings in the law governing the
repair and maintenance of leasehold property. The report was published
prior to the decision in Southwark Borough Council v Mills where the
House of Lords reaffirmed the general rule that the landlord gives no
implied covenant with regard to the condition of the property being
let. The House of Lords held that two tenants of council flats had no
remedy at common law for substantial interference by noise resulting
from the lack of sound proofing. This decision would no doubt have
been regarded by the Commission as further support for its views on the
need for reform.
In the case of Habinteg Housing Association v James Staughton L.J
said in relation to the problem in that case where the landlord was not
liable to sort out an alleged infestation of cockroaches on a housing
estate that, “we are told that the Law Commission has been considering
such a problem. It is to be hoped that they will recommend a
solution. What is more, it is hoped that if they do, Parliament will
carry it out. Judges and lawyers are sometimes reproached when the law
does not produce the right result. There are occasions when the
reproach should be directed elsewhere.”
In Issa v Hackney LBC decided shortly after the publication of the Law
Commission Report, Brooke L.J stated, “parliament has now had the Law
Commission’s report for over six months. The resolution of this
injustice lies in decisions being taken about the allocation and
distribution of public sector finance to the health service and to
local government which are for ministers and Parliament and not for
judges to take in our constitutional scheme of things.”
In Lee v Leeds City Council Chadwick LJ commented on the
recommendation in the report that there should be an implied term as to
fitness for habitation in the following terms, “Parliament has not
found time to give effect to that recommendation. At the least, it has
not done so directly. Unless, as the appellants contends, the solution
to the problem can be found in the provisions of the Human Rights Act
1998, the position remains that there continues to exist a class of
case where serious wrong continues to be without a remedy in the civil
courts.”
Despite the judicial encouragement, the Law Commission report has not
been implemented to date, and it is not clear when, if at all, this may
happen.
Bibliography
Andrews, N, A New Civil Procedural Code for England: Party-Control “Going, Going, Gone”, (2000) CJQ 19, 9
Denehan, E, Dilapidations Law and Practice, 2004, Jordans
Dowding, N and Reynolds, K, Dilapidations, the Modern Law and practice, 3rd Edition, 2004, Sweet & Maxwell
Hall, JG, The Expert Witness, 2001, 3rd Edition, Bary Rose Law Publisher
Hollis, M, Dilapidations: An introduction, 2003, The College of Estate Management
Lightman, G, The Civil Justice Reforms in Practice, (2000), Butterworths
Piggot, MS, Civil Litigation, (2004) Semple Piggot Rocher
Plant, C, Blackstone’s Civil Practice, (2004) Oxford University Press
Vegoda, VH, The Dilapidation Handbook, 2002, London Lark Productions
West, WA, West and Smith’s Law of Dilapidations, 11th Edition, 2001, Estates Gazette
Dilapidations (RICS Guidance Notes), 4th Edition, 2002, RICS Publishing
Effects of the Civil Justice Reforms, (2001) CJQ 20, 301
Emerging Findings: An early evaluation of the Civil Justice Reforms (2001)
Modernising the Civil Courts (2001)
Access to Justice - Interim Report (June 1995)
Access to Justice - Final Report (July 1996)
|